Наверх

Research on More Precise Definition of the Components of the River Water Balance of the Amu Darya and its Main Tributaries and Development of XLSX Routine

Client: BWO Amu Darya

Contractor: SIC ICWC

Implementation period: 01.01.–31.12.2021

Project objective: Carrying out research, developing and testing the routine for calculation of components of water balance of the Amu Darya River and reservoirs in the reaches from Kelif g/s – Bir-Ata g/s, Bir-Ata g/s – Tuyamuyun g/s (Tuyamuyn reservoir), Tuyamuyun g/s – Kipchak g/s, Kipchak g/s – Samanbay g/s.

Work done:

Taking into account the results of the research work in 2020 and 2021, BWO "Amudarya" has been equipped with the methodological, calculation and information base for calculating components of river water balance and reservoir water balance for 4 balancing sites, starting from Kelif g/s to Samanbai g/s, as well as with recommendations on estimation of water losses.

This work allowed defining more precisely the components of water balance of the Amu Darya river in its middle and lower reaches and water balance of Tuyamuyun Hydroscheme reservoirs. As a result, a river water balance mathematical model and algorithms were developed and a relevant routine was implemented to calculate:

Test calculations show that the calculation of the above balance items in the AmuDarya river water balance increases the accuracy river water balance and hence planning of flow distribution and regulation in the Amu Darya and reduces balance discrepancies.